THE HDD PROCESS |
The use of Horizontal Directional Drilling to install crossings under a vast range of surface obstacles was developed in the 1970s combining techniques used in conventional road boring and those used in oil and gas directional drilling. This method is currently used to install pipelines for oil, water, natural gas and waste water as well as conduits for power and fiber optic cables. The main objective is to install such services without using traditional trenching methods, helping to avoid any unnecessary environmental impact and provide added security. |  |
The Horizontal Directional Drilling process generally includes four stages:
- Site Investigation and Design – Project designs start with the gathering of necessary information. This information includes the site survey, including locations of existing pipelines and services, and a geotechnical site investigation. This will determine the tools necessary to successfully drill the crossing and determine the design.

- Pilot Hole Drilling – The pilot hole is drilled from the entry point to the exit point following a previously designed profile and alignment. The drilling tools and rig equipment selected for each job is largely determined based on the results of the geotechnical investigation and the size of the crossing (length and diameter). During the pilot hole drilling, a directional guidance system is used to navigate the pilot hole along its pre-designed profile.
Click here to view illustration
- Hole Enlargement – In small diameter crossings the pipeline may be directly installed in the pilot hole. However in most cases pilot hole enlarging, known as “pre-reaming,” will be necessary. Pre-reaming is required to provide a bore diameter large enough so that the pipeline can be installed in the drilled crossing. Based on the final desired diameter and soil conditions this process may include one or more stages.
Click here to view illustration
- Pullback – Once the drilled hole has been enlarged to the required diameter and cleaned adequately, the pipeline is installed. When applicable, the pipeline is pre-assembled in a single string and placed on rollers prior to pullback. For pullback, a reamer is connected to the drill pipe. Behind the reamer a swivel is connected allowing the drill pipe to rotate the reamer without allowing the transfer of torque to the product pipe. The drill pipe is then pulled back towards the entry point until the pipeline is fully installed.
Click here to view illustration
|
Why HDD?
- Less invasive than the traditional open cut.
- Requires a relatively short set up time.
- Surface disruption is minimized.
- More secure than above ground or trenched installations.
- Can make deep installations and avoid surface obstacles such as rivers, railways, or highways.
|
Intersect HDD Installations
The intersect method is utilized when the length, the soil conditions, or a combination of the two do not allow the use of a single drilling rig to accomplish the bore. In an intersect HDD installation, two directional drilling rigs (a primary and secondary drilling rig) are placed at opposite ends of a project site and start drilling toward each other guided by a precision underground magnetic tracking device. Once the bores are within a pre-determined distance from each other, the primary rig advances its drill string, following behind the secondary rig's retreating downhole assembly. The advancing drill string is then steered toward and ulimately "falls" into the vacated borehole produced by the retreating drill string, creating a continuous single borehole. The borehole is then reamed to the appropriate size and product pipe is pulled.
|
Shore Approach
While the basic steps of a shore approach remains the same as a conventional HDD crossing (i.e. pilot, ream, pullback), there are additional challenges in working within a marine environment.
- Pilot Hole Drilling – The drilling tools and rig equipment selected for each job are largely determined based on the results of the geotechnical investigation and the size of the crossing (length and diameter). During the pilot hole drilling, a directional guidance system is used to navigate the pilot hole along its pre-designed profile. In some cases, the pilot hole is drilled from the primary rig at the entry point onshore to the secondary rig located at the exit point offshore following a previously designed profile and alignment.
Click here to view Illustration Shore Approach #1
- Hole Enlargement – In small diameter crossings the pipeline may be directly installed in the pilot hole. However in most cases pilot hole enlarging, known as “pre-reaming,” will be necessary. Pre-reaming is required to provide a bore diameter large enough so that the pipeline can be installed in the drilled crossing. Based on the final desired diameter and soil conditions, this process may include one or more stages.
Click here to view Illustration Shore Approach #2
- Pullback – Once the drilled hole has been enlarged to the required diameter and cleaned adequately, the product pipe, which will have been preassembled offshore (or assembled onshore and then towed offshore), is readied for installation. The pipeline string is aligned behind the underwater borehole exit point and then pulled into the hole towards the onshore drill rig until installation is complete. Variations to this basic scenario may be needed to fit actual conditions.
Click here to view Illustration Shore Approach #3
Sumber: http://www.coedrilling.com.au/horizontal-directional-drilling-process.php |
No comments:
Post a Comment